Breakdown of a wastewater treatment plant in Weihungszell (Germany) requires replacement new-build and emergency pipeline
What happened
On 24 June, a breakdown at the wastewater treatment plant in Weihungszell made long-term continued operation impossible. The Abwasserzweckverband Oberes Weihungstal then decided on a replacement new-build at the same site. Until the new plant is completed, which is expected to enter operation before Christmas, wastewater is being transported via a 4.5 kilometre emergency pipeline to another treatment works.
Potential impact
The breakdown led to a complete shutdown of the treatment plant and required the construction of a temporary emergency pipeline as well as the replacement new-build of the entire facility. The estimated construction costs amount to around EUR 2.3 million, which are to be partly covered by subsidies. Fee payers in the participating municipalities will have to share the costs.